Let us know your sample critical path milestones. What we generally need to know is:

...

The milestone steps such as "SMS PO SENT".. "SMS RECIEVED". Normally this is between 5 and 10 steps. 

  1. It is best to keep your critical path as simple as possible - have only the major steps that you want to manage. The more steps you have the more steps are needed to maintain by all users.

...

...

  1. The milestone step duration in days.  Please note Indigo8 tracks the durations based off the sample ship date. 

    For example, if it takes 42 Days for the "SMS PO SENT" step to be achieved - we then automatically calculate how long it will take to complete that step working backwards from the ship date - this then marks the due date of that milestone.  
    Ideally it is a good idea to put this on an excel spreadsheet & contact Indigo8 to enter this in the system. Below is an example.


Benefits of the Sample Critical Path

...